Concrete Repair Works (Additional Structures) in Al-Khobar Power & Desalination Plant / Saudia Arabia

The contract includes demolishing, reconstructing and repairing of concrete members

and repairing of electrical system on an area of 109,111 m2. The planned completion

date of the contract is 26 November, 2012.

Total Concrete Amount: 13.951 m3

Total Reinforced Steel : 2120 Ton

Total Structural Steel :113.75 Ton

Total Excavation & Back-fill Amount: 15.647 m3

                                                                                 

                                          

 

Client Saline Water Conversion Corporation (SWCC)

Job Location Saudi Arabia

Contract Date :  03. 11. 2010

Completion Date : 01.04.2015